Portfolio

[Show slideshow]
1800 feet of PVC pipes ordered
adding pins and rebar
After Crystalization of the cyment waterproovingnow Membrane waterprooving added and patched
after new plumbing and new walls
After new wall frames removed
automatic cover closed protecting to dry the tiles
automation wiring
automation witing completet
Bad concrete contractor framing walls bow and require repairs and cutting to shape
Bad framing of conrecet contractors - now need correction and cutting to the shape
Blue Pearl Granite ordered and installed
channel where all ipes and conduits will have to go to the equipment pad
concrete poured walls extended
conditions of the pipes in the walls that needed to be replaced
corners of the granite needed to be shaved polished on site
correcting concrete walls after bad concrete contractor work 10
correcting concrete walls after bad concrete contractor work 2
correcting concrete walls after bad concrete contractor work 3
correcting concrete walls after bad concrete contractor work 6
correcting concrete walls after bad concrete contractor work 7
correcting concrete walls after bad concrete contractor work 8
correcting concrete walls after bad concrete contractor work 9
correcting concrete walls after bad concrete contractor work
crack repairs 2
crack repairs 4
crack repairs 5
crack repairs and instalaltion of waterstops
crack repairs
cut line and rebar preparation
dig out outsides of the walls
Drain for french drain, pavers drain and manual pool drain preparation
drains and sprinkers rerouted on the rear end of the backyard
epoxy preping rebars and walls as well as applying bonding aggent
equipment pad poured and starting to set up
Fittings installed and ready to be cleaned
floor and wall repairs
floor tiling in progress
furniture coming in place
grout work started
Hole drain was made prior of closing the pool
Inside outside digged out
Laser levels to make a decision how to handle level issues (2)
Laser levels to make a decision how to handle level issues 3
Laser levels to make a decision how to handle level issues
Light conduit and plumbing in progress
Light conduit plumbing and drain in progress
Membrane waterprooving of the spa
Mid Wall no good need major repair
New concrete cracks repair
opening outside wall crack locations to repair and re-inforce the walls
Paver corners cut to be even
Pavers and automatic cover installed
Pool equipment close to be completed to be set up
Pool equipment in progress to be set up
pool step tiles completed
Pool Tile completed
Pool Tile installed
preparation of the grounds for the pipes to be run
Preparing skimmer locations and level
preparing walls for new cocnrete
rear backyard kids section basketball trampoline and gym all set and grounds completed with rubber mulch pavers and beach stone
Some old pipes found which were no longer good
Spa floor and bottom plumbing removed and prepaired for new install
Spa jets and plumbing and wall no good have to be broken donw and redone
Spa pipes and floors all bad have to be all opened up and redone
spa prepared for moving forward walls ready
Spa ready to be filled
Spa waterprooved and ready for tile
Sprinkler and french drain work
steps tiling in progress
Tile work and raiy weather complexity
Tiling the pool
Wall preparations for the new extensions of the tops
Walls now cut grinded shaped - repaired to be waterpooved
Wiring automation
workside with pavers loaded onto the deck
wrong level issue requires again walls to be cut and shaped to needed level
1st attempt to dig-out by hand
2006 Sattelite picture of construction
allpoolservices
all-pool-services
Broken hydraulic pipe of the excavator
chanel for runing pipes to the equipment pad had to big opened
Condition of the walls after digging out
DEcember 2015 Project of digging out about to start
Dumbster after Dumpster was getting filled from above
Excavating pool close to half done
Excavating pool started
Excavating started 1
Excavator at the work side
Excavator pipe broke on dropping off heavy stone
Excavator Pool
Front House View
Front View Google streets view (2)
Front View Google streets view
Mid drain unknow holes pipes that were found
Old Backyard - Pool area
Old Backyard
Old Pool Location - Pool under the grass
Old Rear Side
Over a dozen of sprinker pipes to be worked on
Pool Condition after digging out 2
Pool Condition after digging out 3
Pool condition after digging out
Pool Digging out about to start
Pool Excavated and washed - AFTER Excavating Digging out
Pool Half digged oout and manully removed soil
Pool Startig to open up after removing excavating the soil
Professional Engeneering opinions were obtained how to restore walls and cracks
Skimmer boxes were completely damaged gone and only lcoations were visible
Some old pipes found and need to be cleaned from dirt to pressure test
Spa area after digging out (2)
Spa area after digging out
Started digging out arround and outside for pipes and conduits
Steps Condition after digging out and level issue
Steps condition and level issue
this is all first hired contractors were able to dig out by hand